In this entry we want to answer the following questions:

  • Who creates / fills out utility paperwork?

  • Who sends it to customer to sign?

  • Who sends it to electrician to sign?

  • Who submits it to the utility?

  • Who checks with utility if they want to be on site for commissioning? If yes: do they want us or our electrician to be on site? Do they want us to be on site for meter exchange?

    • Where do we save this information underneath the contact?

  • Who schedules meeting with utility if needed (if it’s a meeting where they want us to be on site as well)? 

Avatar
Discard
Author Best Answer

Everything regarding the utilits paperwork is organized underneath the Helpdesk ticket Dein.Solar Interconnection Application. Each ticket contains an overview of the steps supposed to happen in this stage. Here is just an overview of some responsibilites, details are saved underneath the ticket.

Who creates / fills out the utility paperwork?

- Assignee of ticket  (goal: Karoline + Tristan, as of 5/24 Dawid is supporting)

Who sends it to customer to sign?

- Reviewer reviews it (f.e. Tristan)

- Then forwards it to the customer to sign

Who sends it to the electrician to sign?

- Reviewer reviews signed version by customer; saves it underneath "final doc" section (f.e. Tristan)

- Then forwards it to the customer to sign

Who submits it to the utility?

- Reviewer reviews signed version by electrician; saves it underneath "final doc" section (f.e. Tristan)

- Then submits it to the utility

-> Project Manager gets notified once documents (after each step above) are uploaded to the "fnal doc" section, so he/she is aware and can keep the project updated accordingly.

Who checks with the utility if they want to be on site for the commissioning and / or our electrician to be on site for meter exchange etc.?

- Tristan, information gets saved underneath the utility contact.

Who schedules meeting with the utility if needed?

- Project Manager (Oskar)

Who is registering a commissioned system with the Marktstammdatenregister?

Assignee prepares (Karolina) + Reviewer registers it online (Tristan)