Where do I go?
How can I do it?
Do I need to set a specific sequence?
This community is for professionals and enthusiasts of our products and services.
Share and discuss the best content and new marketing ideas, build your professional profile and become a better marketer together.
Where do I go?
How can I do it?
Do I need to set a specific sequence?
Do I understand correctly that the task must now be recorded manually for each project?
Yes this is correct at this time
Project>customers project>
When is this supposed to happen? After material planning and after material is delivered to the jobsite (as of 3/29 we are adding the material delivered to site tasks).
This task sequence # (so order in the project process, lower #s are beginning of process, higher numbers are at the end).
TO create a new tasks for the 55% invoice, it should happen after this tasks is completed
Click Create
Set name of task
Set sequence (so 191, so 192)
Assign who this should be assigned to
Add description