What is the maximum time allowed for processing the applications?

What happens if this deadline is exceeded?

Avatar
Discard
Best Answer

Yes, they have 8 Weeks to react to the application. Within this deadlline he has to do the grid compatibilitiy test and give a point for the power connection. 