Welcome!

This community is for professionals and enthusiasts of our products and services.
Share and discuss the best content and new marketing ideas, build your professional profile and become a better marketer together.

Diese Frage wurde gekennzeichnet
1 Antworten
222 Ansichten

What is the maximum time allowed for processing the applications?

What happens if this deadline is exceeded?

Avatar
Verwerfen
Beste Antwort

Yes, they have 8 Weeks to react to the application. Within this deadlline he has to do the grid compatibilitiy test and give a point for the power connection. 

Avatar
Verwerfen